Scott Hall Progress Photos - January 2016-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - January 2016

Cleanroom mechanical and electrical rough in continues. Cleanroom Air Handling Units installation will start on February 25th. Cleanroom is pressurized; and windows and wall penetrations are covered.

CR Mechanical Rough incleanroom

Furniture and finishes are being installed within the North Wing.

north wing furniturenorth wing furniture

Ceiling Grid, light fixtures, ceiling tiles, sprinklers, etc. installation continues within the North Wing.

Ceiling Grid Installationceiling grid and tilecollaboratory