Scott Hall Progress Photos - April 2016

Scott Hall Grand Opening is scheduled for Aril 30. North Wing building, cafe, and project public spaces will be open for the grand opening. Cleanroom will be opened in summer. Please see the following progress photos form the North Wing. Hamerschlag Drive paving is completed.

north winghillside landscapenorth wing

Hamerschlag DriveHamerschlag Drive

conference roomcollaboratorycollaboratory

North Wing labs are occupied.

north wing labsnorth wing labsnorth wing labs

Cafe and atrium will be open to public by end of April.

cafecafeatrium

Please see the following photos from the green roof and Wean Plaza.

green roofgreen roofgreen roof

Cleanroom mechanical and electrical rough in is ongoing. Cleanroom recirculating air handling units are installed.

cleanroomCleanroom

Porter Hall Entrance Lobby curtain wall is installed. Mechanical and Electrical rough in continues for Area C.

Area Cporter entrance lobby