Scott Hall Progress Photos - September 2015-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - September 2015

9/18/15

Curtain wall installation is completed and curtain wall testing has started. Few remaining panels at the east elevation will be installed once hydromobile is removed.

Curtain WallEast Elevation

Interior drywall framing and boarding is ongoing. Mechanical, electrical, and plumbing rough in is ongoing as well.

mechanical rough inInterior Framing

Please see following photos from cleanroom structural slab, columns, and deck.

cleanroomcleanroom

Concrete slab, columns and deck for the Porter Hall entrance and cleanroom mechanical room are being formed and will be placed within few weeks.

cleanroom mechanical roomcleanroom mechanical room

9/2/15

Concrete slab at the cleanroom mechanical room (south of the Hamerschlag Hall Bridge) is scheduled to be poured on September 3rd. Please see below left photo for formwork and reinforcement installation at this area. On the right, cleanroom connection to Wean Hall is shown. A skylight will be installed at this area within few months.

cleanroom mechanical roomConnection to Wean Hall

Drywall boarding continues with the North Wing floors and tentatively scheduled to be completed by end of September.

Drywall Boardingdrywall Boarding