Scott Hall Progress Photos - May 2015-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - May 2015

5/19/2015

Curtain wall system and dichroic glass installation continues on the south and east elevations of the North Wing as shown in the following pictures. Microscopic layers of metal oxides applied to the surface of a sandwiched, center piece of glass creates the various transmitted and reflective colors in the dichroic glass fins.

curtain wall interiorcurtainwall

First cleanroom deck concrete pour occurred on May 13th. The northwestern part of the concrete deck (future green roof) is poured as shown below. Next pour is scheduled to happen in June tentatively.

cleanroom deckcleanroom deck

Hangers, HVAC ducts, pipes and equipment are being installed throughout the North Wing. Electrical and fire protection equipment and pipes are being installed as well.

mechanical roomriser

5/8/2015

Following are some construction progress photos from the Forbes Avenue and The Carnegie Museum. As shown in the photos, curtain wall installation is completed on the west side of the North Wing.

View from MuseumView from forbes Avenue

5/4/2015

Curtain wall installation continues as shown in the following pictures. Dichroic glasses are being installed on the building envelope as well.

curtain wall installtioncurtain wall installation

curtain wall installationcurtain wall installation

Cleanroom deck rebar installation continues. 

clean room deck rebarClean room deck rebar

As building is being enclosed, mechanical piping and equipment are being installed at the perimeter of building.

Interiorsinterior