Scott Hall Progress Photos - March 2015-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - March 2015

3/25/2015

Concrete formwork installation is completed for the northern part of the courtyard deck. Complicated geometry with multiple sloped surfaces could be seen in the following pictures.

Courtyard DeckCourtyard Deck

Courtyard DeckCourtyard Deck

Hangers and Mechanical equipment and pipes as well as electrical and fire protection equipment are being installed in the north wing.

hangersMechanical equipmentMechanical Room

A group of civil engineering students from ASCE (American Society of Civil Engineers) student chapter had a tour to visit Scott Hall's construction job site on March 20th.

ASCE TourASCE Tour

3/17/2015

Collaboratory stairs structure, located at the south side of the North Wing, is being installed as shown in the below pictures.

StairsStairs

Drywall Framing is started within the North Wing. Pipes and ducts are being installed in the risers.

Dry Wall FramingRisers DuctworkRiser

Pipes and equipment are being installed in the North Wing Mechanical Room. Following pictures show how congested is this area.

Piping in Mechanical RoomMechanical Room Piping

Concrete formwork installation for the cleanroom deck continues. 

Cleanroom DeckCleanroom Deck

3/3/2015

Following pictures show concrete formwork for the courtyard deck which will incorporate a green roof and walk-way after construction completion. It will connect the Hornbostel Mall to the North Wing.

deckdeck

Ducts are being installed in the North Wing risers. Mechanical piping, plumbing, electrical, and fire protection equipment and pipes are being installed as well.

ductshangerspipes