Scott Hall Progress Photos - February 2015

2/19/2015

Structural concrete work is completed throughout the North Wing. As shown in the pictures below, concrete domes beneath the splayed columns and roof concrete pads for mechanical equipment are poured.

417418419

 Following picture shows Scott Hall's North Wing view from the Carnegie Museum of Art.

416

Mechanical, electrical and fire protection equipment, pipes and hangers are being installed within the North Wing. Drywall framing has also started on the 3rd floor of the North Wing. Stairs are being installed as well.

420421422

Concrete formwork and reinforcement in the courtyard is being installed for the courtyard concrete deck, which has a complicated geometry and multiple sloped slabs. This area will be the Scott Hall's green roof in the future.

424423