Scott Hall Progress Photos - April 2015-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - April 2015

4/20/2015

North Wing's envelope, which is a curtain wall system, is being installed and building will be enclosed within less than 2 months. Curtain wall panels are being installed using a spider crane located at the roof of the building as shown below. Moreover, scaffold installation is completed on the hillside. This scaffold will be used for mechanical systems and walls installation. 

Curtain wall installationspider crane

curtain wall installationScaffold

Reinforcement installation on the cleanroom/courtyard deck in the area between Wean hall and Porter Hall continues as shown below. First concrete pour is scheduled for week of April 27th tentatively.

Cleanroom deck reinforcementCleanroom Deck

4/8/2015

A crane is mobilized in the construction job site for reinforcement installation on the cleanroom/courtyard area deck as shown in the below pictures. First concrete pour in this area is tentatively scheduled for week of April 27th.

courtyard deckcrane

Stairs structure is being installed.

stairsstairs

Exterior drywall is being installed in the electrical vault. Pipes and other equipment are being installed throughout the building.

electrical vaultpipesdrywall storage

Vapor barrier is being installed on the north wing roof and penthouse exterior drywall framing is started. Scaffold is being installed by the splayed columns for exterior wall installation.

penthousescaffold