Scott Hall Progress Photos - May 2014-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - May 2014

5/20/2014

260 261 262

Anchor rods are being set in the southern splayed column pile cap, as shown in the photo above.  Rebar is also being placed on the hillside for the large Mat II type foundation pile cap.  This Mat II foundation will contain approximately 198 yards of concrete.

5/18/2014

The hillside continues to be excavated for the installation of pile caps and grade beams.

  257 258 259

5/13/2014

Excavation has progressed on the hillside for the forming of pile caps and grade beams. 

255

Panels are being set within the new pump room. 

256

5/9/2014

Pile cap and grade beam installation continues on the hillside for the North Wing portion of the building.

254

5/6/2014

Sub base soil conditions in the courtyard displayed a high moisture content.  To meet the proper stability requirements, a portion of the soil has been removed, and gravel is being punched into the ground to stabilize the area.  This will provide a proper sub base for the construction of the courtyard slabs.

251 252 253

5/2/2014

The new pump room pad has been poured.  This will be a new mechanical space for Scott Hall.

249 250

5/1/2014

Sheet pile shoring is being installed to support the existing duct bank.  This is needed to excavate deeper for pile cap installation location adjacent to the duct bank.

247 248