Scott Hall Progress Photos - May 2013

5/31/2013

The mechanical contractor is currently finishing core drilling the FMS foundation wall for the chilled water and steam line reroute.

034

5/27/2013

Areas within Roberts Drive near the salt bin have been excavated to verify utility paths.  These locations are being coordinated with the structural foundations.

032 033

5/23/2013

Tie-in locations have been excavated beneath FMS for the new chilled water reroute.

031

5/16/2013

The access road has been completed, and the end of the Hamerschlag Steam tunnel has been removed.

029 030

5/9/2013

An access road is being cut into the site to begin the shoring wall installation.

028

5/2/2013

Manhole 3 and 4 have been placed, and the contractors are setting caps and backfilling the excavated areas.

026 027