Scott Hall Progress Photos - January 2013-Campus Design and Facility Development - Carnegie Mellon University

Scott Hall Progress Photos - January 2013

1/28/2013

Clearing and grubbing of the hillside has been competed and silt fencing has been installed.

1/22/2013

Work at the Wean 4th floor loading dock has been completed.  The loading dock is open for deliveries.

1/18/2013

Please see below for items that have been or are near completion.

  • Roberts Drive will be closed until Sunday for pavement and sidewalk repairs.  Concrete will be poured and finished where the new ductbank was installed for the Lean-to project.
  • Work at Wean 4th floor loading dock near completion. 
  • Work related to the 5KV cable has wrapped up within the corridor, now opening the Wean 4500 corridor.
  • RF shielding complete in Wean 3121.
  • Tree removal on the hillside has been completed.

008 Tree removal015 roberts ductbank

Above you can see the hillside after the trees have been removed.

1/15/2013

Currently, the conduits have been installed for the Roberts 5KV and the contractors are prepare for concrete.

009 5KV 010 5KV

1/4/2013

Currently work related to the Lean-to project continues throughout portions of Wean, Hamerschlag, and Roberts Halls.

  • RF shielding in Wean 3121 is nearly competed.
  • Wean switchgear will be delivered and installed on 1/12.  Please be advised a crane will be used to raise the equipment into the building.
  • Wean 4500 will have a short ramp installed to accommodate occupants while cabling is being installed, this will occur from 1/10 through 1/18.