Scott Hall Progress Photos - September 2012

9/22/2012

Today, the ground breaking ceremonies were held for the Sherman and Joyce Bowie Scott Hall.  This will become the future home of the new Wilton E. Scott Institute for Energy Innovation.  Distinguished guests, donors, and select University members commemorated the event.

Breaking GroundBreaking Ground SpeechBreaking Ground Model

9/17/2012

The Wean Hall duct bank is nearing completion with the majority of the run already buried.  Gas lines were removed this week so the duct bank can continue its path into Wean Hall.

005

9/4/2012

The new Wean Hall duct bank is currently being installed.  The electrical conduits are encased in an aluminum duct with a mixture of sand and gravel.  The shielded duct bank is buried beneath the future corridor surrounding the cleanroom.

001 002

003 004