Installation of overhead Mechanical/Electrical/Plumbing items at the Executive classrooms within the west wing of the first floor of Hamburg Hall:

2016-04-29-image-001


In wall rough-ins in the corridor within the west wing of the first floor of Hamburg Hall:

2016-04-29-image-002


Installation of drywall and overhead Mechanical/Electrical items at the classrooms within the west wing of the first floor of Hamburg Hall:

2016-04-29-image-003


In wall rough-ins and installation of overhead Mechanical/Electrical items at the classrooms within the west wing of the first floor of Hamburg Hall:

2016-04-29-image-004


Framing of the second floor office spaces:

2016-04-29-image-005


Installation of floor underlayment and framing of the office spaces within the second floor:

2016-04-29-image-006