Baker Hall Upgrade Schedule
As reported in the previous issue of Cursor, Baker Hall’s IBM cabling will be replaced with Cat5e cabling by the end of July 2008. Office occupants in Baker may have already been “visited” by workers who are pulling cables to their end points and installing new outlets.
The re-cabling and outlet work started on the Hunt Library end of the building and will continue on toward Porter Hall. The most current schedule is included below:
|
Start date
|
Rooms
|
Status |
|
4/1/08
|
A60A - A60Z
|
In progress
|
| 161A - 161G |
160 - 182
|
|
4/7/08
|
259,261,262,263,265,267
|
In progress |
260A - 260H
|
In progress |
|
4-14-08
|
155 - 155F
|
In progress |
255A & 255B
|
In progress |
356 - 356F
|
In progress |
4/21/08
|
145 - 145Q
|
In progress |
245 - 245S
|
In progress |
345 - 345P
|
In progress |
455 - 455L
|
In progress |
4/28/08
|
446 - 446J
|
In progress |
| 340A - 340V |
In progress |
342A - 342G
|
In progress |
346-346E
|
In progress |
239 - 239A
|
In progress |
240 - 240H
|
In progress |
246A - 246C
|
In progress |
139 - 139C
|
In progress |
| 143 |
In progress |
140 - 140H
|
In progress |
150
|
In progress |
5/5/08
|
To be announced
|
|
For an installation schedule of new cabling, outlets and wireless access points in other buildings around campus, visit the Wireless Andrew 2 project page.