Baker Hall Upgrade Schedule

As reported in the previous issue of Cursor, Baker Hall’s IBM cabling will be replaced with Cat5e cabling by the end of July 2008. Office occupants in Baker may have already been “visited” by workers who are pulling cables to their end points and installing new outlets.

The re-cabling and outlet work started on the Hunt Library end of the building and will continue on toward Porter Hall. The most current schedule is included below: 

 Start date

 Rooms

 Status

 4/1/08


 A60A - A60Z

 In progress
 161A - 161G
 160 - 182

 4/7/08


 259,261,262,263,265,267

 In progress
 260A - 260H
 In progress

 4-14-08

 155 - 155F

 In progress
 255A & 255B
 In progress
 356 - 356F
 In progress
 4/21/08
 145 - 145Q
 In progress
 245 - 245S
 In progress
 345 - 345P
 In progress
 455 - 455L
 In progress
 4/28/08
 446 - 446J
 In progress
 340A - 340V  In progress
 342A - 342G
 In progress
 346-346E
 In progress
 239 - 239A
 In progress
 240 - 240H
 In progress
 246A - 246C
 In progress
 139 - 139C
 In progress
 143  In progress
 140 - 140H
 In progress
 150
 In progress
5/5/08
 To be announced
 

For an installation schedule of new cabling, outlets and wireless access points in other buildings around campus, visit the Wireless Andrew 2 project page.