News and Updates-Campus Design and Facility Development - Carnegie Mellon University

Current and Future Work*

Two Week Look-Ahead

  • Asphalt pavement within the courtyard will begin to be removed.
  • Backfill within the courtyard, against the new pump room foundation walls.
  • Concrete pours within the Courtyard and North Wing, noise and vibration may be more noticeable during this time.
  • Drilling and pouring of remaining North Wing caissons and pile caps.
  • Masonry Restoration Project: Masonry restoration work on Wean Hall and Hamerschlag Hall is underway.  Please see contact information below in 'Important Notifications' for issues related to the Masonry Restoration Project.

Important Notifications

  • Hamerschlag Hall E Level north exit will be closed 10/7/13 for the duration of the project(Fall 2015).  Please exit via the first floor main entrance in the case of an emergency.
  • Masonry contractors for an adjacent University Project will be working on Hamerschlag, Wean, and Doherty Halls throughout the Fall.  Occupants within these areas may experience some noise and vibration, please contact your building's Facility Director or Karen Spells Attn: Edward Hydzik for masonry related comments.
  • The FMS Pedestrian Bridge is closed until work in that area finalizes.
  • Hamerschlag Drive will close on 4/29/13 for the duration of the project(Fall 2015).  Access to Gates Garage will be maintained via Boundary street and under the CIC garage.  Please see detour maps below.
  • Access to the Roberts loading dock is limited to scheduled deliveries only.
  • Pedestrian access will not be permitted within work zones.

Emergency Exiting Plan

During the construction of Scott Hall, many activities will occur within the Hamerschlag Courtyard.  Unauthorized personnel will not be allowed within the area due to safety regulations.  Please use the following detour maps as reference to new exiting strategies.

hh exit wean exit

 porter detour HH E Level

Hamerschlag Drive Closure Detours

*During the above mentioned closures, please reference the maps below for detailed routes.


View Larger Map


View Larger Map

If you have any questions please contact Max Dorosa, maxd@andrew.cmu.edu or 412-268-8936.

*Please note that portions of work may produce noise within the immediate area, and all efforts will be taken to reduce any noise.  We apologize for any inconvenience, and we appreciate your understanding and cooperation during this time.

noise chart

Progress to Date

Please see below for items of importance and photos depicting current work on the Scott Hall Project, Thank you.

4/9/14

233 234

232

The pump room foundation walls are being backfilled as waterproofing continues to be installed.

4/4/14

Pump room foundation wall waterproofing is being installed.  Once an area is waterproofed, blue protection board is installed prior to backfilling.  Waterproofers work their way up as the levels of the wall are accessible with the backfill progress.  A water expansive bentonite material is installed(shown in white), where new construction waterproofing meets existing buildings(Wean Hall).

230 231

3/25/14

226 227

228

229

The rebar and foundation wall forms continue to be installed on Mat 3.  Concrete can be expected to be poured within 2-3 weeks.  Additional photos below depict areas that are being excavated around North Wing caissons for the forming of pile caps.

3/21/14

While much of the construction is currently outside, there is also work happening beneath our feet in utility tunnels.  The new lines shown below are being installed to accommodate additional tie in points for the new building's demand, and to remove old lines from the site of new construction.

222 223

224 225

3/14/14

The sidewalk outside of the south entrance to Hamerschlag Hall has been removed for the installation of the new handicap compliant ramp.  This ramp will include a new railing that will double as the mockup for the Scott Hall collaboratory staircase.  This ramp is expected to be completed within the next 2 weeks.  Additional photos show wall forms for the Mat 3 elevator foundations are going up and rebar is being set.

216 221

219

220

3/11/14

Wall forms are being removed from the new pump room foundation walls as the remaining pile caps in the pump room are being formed.  Rebar for the Mat 3 foundation walls are beginning to take form.  The remaining caissons and pile caps on the hillside are being drilled, formed and poured.  At this time there are 22 caissons that remain to be drilled. 

211 212

215

209 210

Dichroic glass samples have been installed to the side of the construction trailer for review.

214 213

206 207 208

3/7/14

Tunnel utility connections have been made, which reroutes existing utilities from the site of the new cleanroom.  The new valves and piping shown below were installed throughout the past couple weeks.

204 205

2/27/14

198 203

Wall forms and rebar are in place for the new pump room foundation.  Concrete is scheduled to be poured Monday, 3/3/14. 

2/20/14

Foundation walls in the courtyard pump room are being formed and rebar is being set.  This process will take approximately 1.5 weeks and concrete can be poured subsequently.  Work continues with mat 3 foundations and caisson drilling on the hillside.

195 196 

197

2/13/14

The project team refers to the largest mat foundation pad for the project as "Mat 3".  This foundation essentially acts as an anchor for the portion of the building that cantilevers over the hillside.  Mat 3 formwork and rebar has been installed concrete is being poured.  There is approximately 216 cubic yards of concrete just within this piece of the foundations; that's 24 concrete truck deliveries. 

187 188

189 191

190

The foundation wall forms are being installed as rebar is completed for the new pump room.

192 193 194

2/5/14

Foundation walls are being formed within the pump room space, while the mat 3 pad(3rd photo) is being finalized for concrete to be poured.

184 185 186

1/31/14

18 trucks of concrete were delivered on site today for the pump room grade beams and pile caps.  15+ workers were on site and coordinated the concrete trucks and pump with the pour locations.

182 183

180 181

Outpak Washout boxes provide LEED certified disposal of slump testing on site.  Slump testing is essentially placing an amount of concrete outside of the forms to ensure the proper mixture thickness and fluidity.  To ensure there is no contamination to surrounding areas, this product allows an easy, clean, and safe alternative to on site slump testing.

178 179

As you can see below, the pump truck had a reach of over 150' to deliver concrete to the proper locations.  As a testing requirement, concrete sample cylinders are collected every 50 yards per the engineers specified testing requirements.  The cylinders shown here are only a small handful of what has been collected to date.  These cylinders will be tested, by breaking them, at certain cure intervals to ensure the concrete is meeting the specified strength.

177 175 176

173 174

1/23/14

Grade beam and pile cap forms are in place.  Final heating preparations will need to be done prior to the scheduled concrete pour.

171

170 172

169

1/20/14

The Pittsburgh Fire Department visited the construction site today for a inspection to review temporary exit strategies and detours.  There are 8 exits that have been affected by the construction.

168

1/17/14

The ramp and stairs have been removed from both locations on Wean Hall.  These exits have been closed for the duration of the project.  A walk through with the city fire department is scheduled for 1/20/14 to review exit paths and detours.  Pile cap forms and rebar are being installed.  Concrete for the pump room and large elevator(mat 3) pile cap is expected to come during the week of 1/27/14.  Installation of the main shoring wall tie-backs are continuing; approximately half of the tiebacks have been installed.

159 160

161

162 163

164

165 166 167

1/3/14

The concrete stairs connected to Wean and Porter Halls is currently being demolished.  This demolision should wrap up within the next week.

157 158

12/27/13

Pump room pile cap rebar has been delivered and pile caps are being formed.  The new loading dock are is being excavated to form pile caps.

155 156

154

12/23/13

Caissons within the pump room have been completed.  Next, pile caps and footings will be formed and poured.  The shoring wall tiebacks are scheduled to begin now that all caissons are completed in this area.

153 152

151

12/11/13

The construction crew continues to drill and pour caissons on the hillside and within the pump room. 

150

12/4/13

147 149

148

The construction site is teaming with activity as 2 rigs drill caissons, multiple excavators prep for caisson locations, and a crane is situated to install caisson reinforcement.  Crews are currently drilling caissons for the southern splayed column clusters, and within the pump room.  57 caissons have been drilled and poured to date.

11/25/13

The FMS salt shed has been completed and is ready for salt to be delivered.

146

11/21/13

A Town Hall Meeting will be held today from 5-6pm in McConomy Auditorium.  Please follow this link for the presentation that will be given at the meeting.

11/7/13

141 142

The caisson coordinates within the new pump room have been surveyed and will be drilled within the next week.

11/6/13

The Hamerschlag Shoring wall has been completed.  The remainder of the sanitry reroute will take place through the next two weeks.

139 140

138

137

10/30/13

Caissons are currently being drilled and poured where the salt bin once was.  Once these caissons are completed, tiebacks (pictured and described below)  can be installed in the main shoring wall.  This will allow for the remaining excavation of the north wing hillside, and accommodate drilling of the remaining caissons.

134 135 136

133

Tiebacks, shown in the photos below, are steel cables that are inserted through shoring wall piers that act as an anchoring mechanism for a retaining wall that is being installed.  Essentially the tiebacks are supported by the mass of earth that the shoring wall is designed to retain.  The images below show that all tiebacks have been installed.  The courtyard area will be excavated approximately another 12' to allow for the construction of the new pump room and the final relocation of the sanitary line shown piped in these photos. 

130 131 132

129

10/22/13

The removal of the Wean Hall areaways has allowed for the lower portion of the sanitary reroute to be completed.  During the excavation, a foundation drain for Wean Hall was found and has been tied into the sanitary reroute.  In order for the sanitary reroute to be completed, a shoring wall against Hamerschlag Hall had to be installed to allow for the deep excavation so close to the building.  The shoring wall is currently being installed, and grade will be excavated approximately 12 feet below its current level.  This excavation is not only for the installation of the sanitary reroute, but also to construct a lower pump room that will service the new and existing services.

120

121 119 sanitary

122 124 123

10/18/13

The campus salt and mulch storage has been relocated to the lot across the tracks.  The base of the storage bins have been asphalt paved and concrete foundation blocks have been arranged in U-shaped configurations.  The finishing touch will include barrel-arched roofs to protect the bins from the weather.  Please see the series of photos below depicting the construction of these storage bins.

125 126 127 128

10/10/13

115 116

The lot across the tracks has been graded, and a stone drive is being installed to access the new location for the FMS salt shed and mulch pile.  A new entrance from boundary street has been created to stay the proper distance away from the Railroad tracks.

117 118

10/7/13

112 113

114

Excavation at the western portion of Wean Hall has completed for the removal of the concrete areaways beneath the transformer garage doors in the photos above.  These concrete areaways will be removed to allow for the construction of the new Scott Hall elevator mat slab foundation.

9/27/13

The lower manhole is being set within the excavation for the sanitary reroute.

110 107

108 109

9/20/13

The temporary sanitary reroute within the courtyard has been installed.  This reroute diverts the sanitary away from the existing route while the new permanent line can be installed.

104 105 106

9/13/13

Work on the shoring wall continues, while the storm/sanitary line within the courtyard is temporarily rerouted.  The storm/sanitary line will be permanently reouted after the excavation and shoring activities within the area are complete.

097 098

099 100 101

094 095 096

9/10/13

A group of students from the School of Architecture who have based a construction practices course around the Scott Hall Project receive a tour of the site.

092 093

8/26/13

The excavation of the courtyard continues to progress.  Currently the majority of dirt has been removed through the Porter Parking Lot.  We remind pedestrians to follow posted safety signs while near construction zones.

086 088

087

Drilling of the first caisson is nearly complete.  The rebar reinforcement cage, which will go into the newly drilled hole, is situated in a staging area.  Once the rebar is installed within the hole, concrete will be pumped in place which will create the caisson.

089 090 091

8/19/13

The shoring wall process begins with the drilling for shoring piles which are steel columns that will have wire tendons shot into the earth behind the wall to keep this from caving in.  Once the piles are installed, wood lagging is used to temporary hold dirt behind the wall back while the dirt in front is excavated.  Once the excavation reaches the correct depth, concrete panels will be place between the steel piles, which will remain as the permanent shoring structure.   

084 085

8/12/13

The outer chiller wall has been removed and dirt is being removed from the courtyard to prepare for the new pump room construction.

082 083

8/7/13

Drilling on the hillside has begun.  Soldier piles for the permanent shoring wall are being drilled currently.  Once the wall pile are drilled and set, the contractor will move to caissons across the hillside and within Hamerschlag Drive.

078 079

080 081

7/31/13

The retaining wall from the original chiller location has been removed and dirt is being excavated from the courtyard.  The excavation throughout the entire courtyard will drop the elevation by approximately 10' to allow space for an engineered fill material and the construction of the new concrete floor slab.  We would like to remind pedestrians to stay out of marked construction areas for their safety due to the high level of construction activities.

076 077

7/25/13

The second chiller has been relocated and piping is currently being installed.

074 075

7/22/13

The chilled water reroute through Hamerschlag D Level has been completed.  The water lines are running with no issues.

071 073

072

7/19/13

An adjacent University Project, Masonry Restoration, is underway on Wean, Hamerschlag, and Doherty Halls.  The scope of work includes repairing damaged and spalled concrete to Wean Hall by hammering and sawing necessary areas, patching, and sealing the entire facade.  Hamerschlag Hall will be re-pointed in damaged regions with minimal brick replacement.  The arched masonry underside of Doherty Hall will be removed and re-supported with steel support brackets.  This work will continue alongside the Scott Hall construction, however if you feel disrupted by the masonry repairs please contact your building's Facility Director or Karen Spells Attn: Edward Hydzik with Campus Design Facility Development.

Work scheduled:  Masonry contractors will be cleaning and removing caulking on the south elevation mall area of Wean.  They will continue cutting and grinding on the west and northwest side of Wean.  Removal of the brick and granite lentils on the Doherty Bridge will continue, and welders will also be installing support brackets.

7/17/13

Exits in the courtyard are starting to be affected by demolition and other construction activities.  Please review the detour maps above for a description of proper exiting procedures and paths.

7/15/13

The first chiller was lifted into place today.  It will take the remainder of the week to pipe to the chiller and complete the hookup before the 2nd chiller can be relocated next week.

066 065

The new construction has been delivered to the Porter Parking Lot.  The electric and data will be hooked up next week and the construction team will begin moving in the following week.  Also, the nitrogen pad has been formed for the relocation.

067 068

7/12/13

The demolition of the salt bin continues.  Multiple utility lines(abandoned and active) have been found under and near the excavation site.  It has been noted that the salt bin was constructed on the same foundations of an original coal hopper that fed Hamerschlag Hall.  These foundations are being excavated also, which has led the excavation to lower elevations than anticipated. 

061 062

In order to prepare for the Cleanroom Chiller relocation the Hamerschlag server room roof has been removed.  This space will be prepped for the first chiller relocation scheduled for 7/15/13.

063 064

7/11/13

The chilled water reroute has been backfilled and Roberts Drive has been returned to normal use.  Final backfilling remains within the FMS loading dock are.  The excavated areas will be re-paved in the coming weeks.

057 058

The reroute on upper Roberts drive is finalizing and the road will be backfilled by the end of next week.

059 060

7/1/13

The new chilled water lines have been installed within Roberts Drive near FMS.  The lines will be backfilled later this week.

055 056

6/24/13

Spot excavations within planters and on the Wean Hall 4600 roof/plaza are being explored to supply the design team with a roof composition detail of current conditions.  Portions of Wean Hall will experience intermittent periods of noise and slight vibration during the next 2 weeks.  We apologize for any inconvenience.

049 050

The remaining walls of the lean-to have been removed and the excavator has begun sorting the debris for disposal/recycling.

051 052 053

6/21/13

The lean-to within the HH/Wean/Porter parking lot is currently being demolished.  During this time we ask all pedestrians near the area to maintain a safe distance from the construction zone barrier.  The Wean Hall fire stair egress, 4129, should be used only during an emergency.

045 046

047 048

6/19/13

The first casework mock-up has been delivered and assembled in Smith Hall.  Two more mock-ups are expected to be delivered in the next two weeks and the fourth and final to be delivered in July.

043 044

6/11/13

The new water and steam lines are currently being set into place.  The team will continue to set the remaining lines, shoot as-built coordinates, and back fill once complete.  A coal hopper was discovered beneath the salt bin, and the crew on site is exploring the depth of the hopper and the impacts of it's removal.

037 038 039 040

041 042

6/7/13

The demolition of the salt bin on Roberts Drive has begun.  The majority of the structure will be removed by 6/11/13.

035 036

5/31/13

The mechanical contractor is currently finishing core drilling the FMS foundation wall for the chilled water and steam line reroute.

034

5/27/13

Areas within Roberts Drive near the salt bin have been excavated to verify utility paths.  These locations are being coordinated with the structural foundations.

032 033

5/23/13

Tie-in locations have been excavated beneath FMS for the new chilled water reroute.

031

5/16/13

The access road has been completed, and the end of the Hamerschlag Steam tunnel has been removed.

029 030

5/9/13

An access road is being cut into the site to begin the shoring wall installation.

028

5/2/13

Manhole 3 and 4 have been placed, and the contractors are setting caps and backfilling the excavated areas.

026 027

4/24/13

Please find attached the Town Hall Presentation given at the meeting held last night.

4/17/13

Manholes 6 and 7 have been set and our crew is in the process of excavating for manhole 5.

022 023

024 025

4/8/13

Manhole 8 has been placed and the construction crew continues work on manhole 7.  Once this work is completed the Roberts Drive will be re-opened temporarily.

3/28/13

During the excavation for the sanitary relocation, the Hamerschlag tunnel has been unearthed and the contractors have begun to demolish portions of the tunnel to make way for the new manhole that will be installed.

020 021

3/22/13

Roberts Drive will be closed Monday morning for the installation of the new manholes for the sanitary maintenance.

3/11/13

Excavation parallel to the lower portion of FMS drive has begun to identify the exact location of the 15" sanitary line.

016 017

3/5/13

In order to prepare the site for the new sanitary line, the radius wall on Roberts pedestrian ramp had to be removed.  A temporary set of steps have been built to maintain access to this entrance.

018 radius wall 019 radius wall

2/26/13

The contractor is on site and excavation for sanitary utilities has begun.  Please see the images below for a detailed looked at this process.

013 sanitary 014 sanitary

2/22/13

Beginning Monday the Road closures to Roberts Drive and pedestrian detours will begin.  Please review the maps posted above and allowed yourself additional time to reach your destination.

2/15/13

The new Wean Hall skylight mockup has been installed and can be found in the courtyard.  This mockup demonstrates the actual height and angle of the proposed design.

012skylightmockup

2/14/13

Please see the following diagram for a detailed view of the Roberts Drive closure.

2/8/13

  • The ductbank along Roberts Hall has been completed and backfilled on the hillside.
  • The shoring and excavation contractors begin to plan site work the week of 2/18/13.

1/28/13

Clearing and grubbing of the hillside has been competed and silt fencing has been installed.

1/22/13

Work at the Wean 4th floor loading dock has been completed.  The loading dock is open for deliveries.

1/18/13

Please see below for items that have been or are near completion.

  • Roberts Drive will be closed until Sunday for pavement and sidewalk repairs.  Concrete will be poured and finished where the new ductbank was installed for the Lean-to project.
  • Work at Wean 4th floor loading dock near completion. 
  • Work related to the 5KV cable has wrapped up within the corridor, now opening the Wean 4500 corridor.
  • RF shielding complete in Wean 3121.
  • Tree removal on the hillside has been completed.

008 Tree removal

015 roberts ductbank

Above you can see the hillside after the trees have been removed.

1/15/13

Currently, the conduits have been installed for the Roberts 5KV and the contractors are prepare for concrete.

009 5KV 010 5KV

1/4/13

Currently work related to the Lean-to project continues throughout portions of Wean, Hamerschlag, and Roberts Halls.

  • RF shielding in Wean 3121 is nearly competed.
  • Wean switchgear will be delivered and installed on 1/12.  Please be advised a crane will be used to raise the equipment into the building.
  • Wean 4500 will have a short ramp installed to accommodate occupants while cabling is being installed, this will occur from 1/10 through 1/18.

12/21/12

Recent completed items related to the Lean-to project are as follow:

  • Conduit installed in Wean Senate Room.
  • Wean 3121 demo and 2nd floor conduit installation complete.
  • Conduit installation in HH interstitial space, above cleanroom, and road crossing have been completed.

12/10/12

The design and construction team are currently working on VE efforts for the project.  Please see below for a quick list of items worked on this week.

  • Fencing surrounding the construction site.  Clearing and grubbing to follow.
  • Most demolition in Wean and HH is complete while the installation of conduit begins.
  • Installation of conduits above clean room in HH, in HH steam tunnel, and on the 3rd floor Wean Hall corridor 3500 has been started.
  • Majority of conduit installation complete in Wean Senate Room, Wean 2nd floor 5KV Room, HH Interstitial space, and above HH Clean Room.
  • Road conduit installed, pour concrete and backfill to happen in coming weeks.
  • Installation of conduit across Roberts Drive to HH has begun.
  • Start conduit runs up hill from manhole #27 to interstitial space.
  • Roberts Drive closed Saturday 12/15, 12/22, 12/29, and 1/5 from 6:00AM to 6:00PM.
  • Two sidewalks along Roberts Drive will be closed and remain closed until 1/5.

12/3/12

The lower parking lot across the tracks will be closed for the mobilization of Jendoco's construction trailer and storage box.  Roberts Drive will be plated during the week while work continues on the trench excavation during the weekend road closures.  This will also keep the sidewalks in the vicinity temporarily closed during this time.  Demolition in Wean and Hamerschlag is nearly complete for the installation of new conduit to occur next week.

11/27/12

The current timeline of schedules events is as follows:

  • 12/3/12- Mobilization of the Jendoco Construction trailer and storage box to the railroad parking lot.  At this time the lot will be closed to the parking that currently occurs in the lot.
  • 12/5/12- Install temporary security fencing at the railroad lot around the lay down and trailer areas.
  • 12/6/12- Install security fencing at the North Wing hillside.  This includes the lower Roberts parking area that is currently being used by FMS for storage and parking.  We will begin clearing and grubbing the hillside.  This includes the removal of the trees and mulching them.  This will continue for one week.
  • 12/10/12- Selected subcontractor for the Excavation and Shoring Bid Package(BP-01) mobilizes their trailers and equipment to the railroad lot.
  • 12/17/12- Work begins on the relocation of the 15" sanitary line.  This includes work on Roberts Drive adjacent to the salt shed.  The current plan is to start work on the hillside and during the winter break move up into Roberts Drive with the deep trenching.  The road will be plated when possible.  Work atop Roberts Drive will continue for two weeks.
  • 1/3/13- Retaining wall soldier pile drilling will begin and continue for two to three weeks.  Drilling from atop Roberts will be necessary.  This will at times limit access to Roberts Drive.  This will be closely coordinated with the salt shed usage, nitrogen refilling and deliveries to Hamerschlag Hall.
  • 1/21/13- Mass excavation will begin at the North Wing and will follow the progress of the shoring wall installation.
  • 2/4/13- Excavation and Shoring(BP-01) work is in its final stages of completion.  Jendoco prepares for the mobilization of the foundation bid package(BP-02), subcontractor to begin North Wing foundation and utility work.  An updated timeline will be issued for this scope of work.

p1
p2

Please click on the Site Phase layout Diagrams above for a more detailed view of each.

11/26/12

Two separate sections of sidewalk along Roberts Drive will be removed, closing the sidewalk and center door along the road to Roberts Hall.  This area will be closed from 11/28 through 12/26.  The center door will be available for emergency egress only.  Detour signs will be posted at the south and north ends of the sidewalk.

Roberts Drive will be closed on weekends throughout December.  The schedule for closing is December 1, 7:00 AM until noon, December 8-9, December 15-16, and December 22-23 from 7:00 AM Saturday until 5:00 PM Sunday each week.  A trench will be cut across Roberts Drive for the installation of the new duct bank and steel plating will be installed for the weekday traffic.

11/16/12

Mobilization for work on the Hamerschlag Lean-to will begin Monday 11/19.  Work will begin in the F level of Hamerschlag, and occupants may experience intermittent periods of noise.  There will be a combination of mechanical duct work, water and stream piping, and electrical fixtures removed from the space. Some additional work will include Wean Hall 4505(drilling) and 3121(interior partition removal).  All efforts will be taken to reduce any noise during this work.  We appreciate your understanding and cooperation during this time.

Excavation work done to Roberts drive this week is wrapping up, concrete will be poured Monday, and barriers will be removed Wednesday.

11/8/12

Excavation work along Wean Hall parking lot will resume today and tomorrow from 7:00 am until 3:30 pm each day.  Work is anticipated to be finished on Monday 11/12.  Efforts will be taken by our team to minimize any disruptions as much as possible.  Please watch for notices regarding future construction activities.

Excavation work will be done on Roberts Drive and will continue throughout next week.  Due to safety requirements, sections of the sidewalk will be closed and pedestrians will be redirected around a construction barrier.  Work on Roberts drive will continue through next week, ending 11/19.  Pedestrians and traffic will be directed around the work area with cones and barriers during this time.  We appreciate your patience and cooperation during this work.

11/2/12

The design team will join the engineers and construction team on 11/5 and 11/8 to reconcile design choices.

10/24/12

A banner with a rendering of the future Scott Hall has been hung on Wean Hall pointing out the location of our campus' newest addition.  This addition will greatly strengthen inter-campus connectivity.

Banner

10/22/12

A Town Hall Meeting has been organized for Today in Rangos Hall.  Design specifics of the new Scott Hall will be announced and discussed by the Architect and the Campus Design office.  Please follow this link for a digital copy of the Town Hall Presentation.  Below are a few renderings that will be displayed at the meeting.

Town Hall Presentation

Hamerschlag  wean entry

mall  view from Ham

9/22/12

Today, the ground breaking ceremonies were held for the Sherman and Joyce Bowie Scott Hall.  This will become the future home of the new Wilton E. Scott Institute for Energy Innovation.  Distinguished guests, donors, and select University members commemorated the event.

Breaking ground

Breaking ground 6 Breaking ground 7

9/17/12

The Wean Hall duct bank is nearing completion with the majority of the run already buried.  Gas lines were removed this week so the duct bank can continue its path into Wean Hall.

005

9/4/12

The new Wean Hall duct bank is currently being installed.  The electrical conduits are encased in an aluminum duct with a mixture of sand and gravel.  The shielded duct bank is buried beneath the future corridor surrounding the cleanroom.

001 002

003 004

8/23/12

3D modeling and clash detection has become a major method to expedite the design coordination process.  Combining the consultants models allows all members of the team to visually focus on areas of the building and review issues that may arise.

cafe colab

cleanroom exterior

4/2/12

A telephone and electrical duct bank have been exposed in order to plot there coordinates within the hillside.  This will enable the design team to plan foundations more accurately.

exposed utilities 4300

3/23/12

Exploratory work continues.  Site utilities are being located and identified.  Test holes are plotted and excavated with the help of previous campus surveys and historical data.  Once a utility is found, coordinates are shot and points are transferred and modeled into a 3D site model.

mini on hillside 1 exposed line 3.23.12

3/13/12

Starting today our project team will begin exploration work to locate approximate locations of site utilities in the hillside.  Throughout the next few weeks our CM, Jendoco, will be spot excavating on the hillside to locate the paths of storm, water, steam, and electrical lines which are located in the area.  A mini-excavator will be brought on site to facilitate the efficiency of locating utilities.

Efforts will be taken by our team to minimize any disruptions as much as possible.  Please watch for notices regarding future construction activities. We appreciate your patience and cooperation during this work.